SH 99: IH 10(E) TO SH 146
Segment I-2

February 19, 2008, a ribbon-cutting celebration commemorating the completion of the first phase of Segment I-2 (IH 10 to FM 1405) was held, and the segment was opened to traffic on March 25, 2008. Phase 2 of Segment I-2 (FM 1405 to SH 146) is currently under design.
Construction of Phase I from IH 10 south to FM 1405 was let in Aug 2003 with completion scheduled in Oct 2007.
Construction from FM 1405 west along former SP 55 and BUS 146 will proceed as travel demand warrants and construction funds are available.
TxDOT proposes to toll Segment I-2 from IH 10 to Fisher Road.
A public meeting was held on October 20, 2005 to gain public input addressing the concept of operating this proposed main lane section of SH 99 as a toll facility. An environmental reevaluation study is being prepared to address the proposed tolling. Click here to view photographs taken at the public meeting.