I-45(S) to SH 288
Segment B

Segment B is a proposed 28-mile, four-lane, controlled access toll road with intermittent frontage roads from I-45(S) (the Gulf Freeway) in League City, towards SH 35 in Alvin and on to SH 288 (the South Freeway) near Rosharon through Galveston and Brazoria Counties.

For Segment B, the alternative alignments were developed within the project area to fulfill the need and purpose of the project, to minimize potential environmental impacts, and to respond to public/landowner and resource agency comments. Identification of the Recommended Alternative Alignment was based on public and resource agency input, and analysis and comparison of the potential effects on the physical, biological, and human environments of each alternative alignment.

The Recommend Alternative Alignment is shown in the maps below. Click on the individual squares to view detailed maps of Segment B. These squares indicate the limits of the detailed maps for this segment. The detailed maps are large files and may take a few minutes to download depending on the speed of your internet connection. Once in the detailed maps, use the zoom button in the toolbar to view the maps at 100% of their original size. A map with the studied Selected Candidate Alignments can be found on the "Documents” page.

2011-June recommended route:

Click here for overview of Grand Parkway Segment B DEIS Alignment with Google Maps.

To view an overall layout of Segment B, click here. The overall layout map is a large file and may take a few minutes to download. For a low resolution file of the overall layout, click here.

Notice of Availability

Record of Decision

Summary Official Record of Response to Comments on FEIS

The Segment B Final Environmental Impact Statement (FEIS) was signed by the TxDOT Environmental Division (ENV) on May 25, 2016 and was published in the Texas Register and Federal Register on June 3, 2016. Comments will be accepted until July 11, 2016.

Addendum to Summary Official Record of Public Hearing for DEIS

Segment B Study - Summary Official Record of Public Hearing for DEIS

 

To download or read the document, please click here.

To send your comments for Segment B, email SegmentBcomments@grandpky.com

On August 21 and 23, 2012, TxDOT hosted Public Hearings to discuss proposed improvements in the SH99 corridor from SH 288 to IH 45 (S). For details, here is the Notice of Segment B Public Hearing. Also here is the Segment B Public Hearing Handout and the Segment B Public Hearing Presentation.

Notice of Availability and Extension of Comment Deadline of the Segment B DEIS in the Texas Register Notice of Availability for Segment B (June 29, 2012) and Extension of Comment Deadline for Segment B (July 27, 2012).

Notice of Availability of the Segment B DEIS in the Federal Register Federal Notice of Availability for Segment B (June 29, 2012).

The Segment B DEIS was signed by the Federal Highway Administration on June 6, 2012 and was published in both the State and Federal Registers on June 29, 2012.

Send your comments regarding the Segment B DEIS to segmentBcomments@grandpky.com.

The Segment B DEIS has been organized in a two volume set. Volume I contains the DEIS and Figures. Volume II includes Exhibits and Appendices A through H.

Prior to opening this document, please right click and "save target as" to your server or hard drive. Due to the size of the file(s) it will time out or lock up your computer if you try to open from this location.

Segment B DEIS Volume I

Segment B DEIS Volume II

Additional information concerning the schedule can be found here.

This application requires Adobe Reader. To view maps at optimum quality, Adobe Reader Version 7.0 or higher is required. If using lower versions, some quality may be sacrificed. Click here to download the latest version of Adobe Reader for free.